Skip to content

Institut Mihajlo Pupin · power unit control

DCS VIEW Power power unit control

VIEW T-PowerVIEW H-PowerAtlas MaxIEC 61131

A distributed control system for thermal and hydro power plants: VIEW T-Power for TPPs and VIEW H-Power for HPPs. Developed since 2004 by the institute’s subsidiary IMP-Automation & Control: Atlas Max controllers, VIEW software packages, compliance with the IEC 61131 series.

  • 40+redundant controllers — two units of TPP Kostolac B
  • 348.5MW — a TPP Kostolac B unit under the institute’s DCS
  • 1328MW — the Đerdap HPPs, modernization since 2006
Unit control room, TPP Kostolac B · an institute reference site
Unit control room, TPP Kostolac B · an institute reference site

How it works · DCS VIEW Power

One unit — one distributed system.

  1. Boiler, turbine, generator and auxiliaries — or a hydro unit with its generator and block transformer. Equipment of different makers under one system.

  2. Redundant Atlas Max controllers run the process areas: more than 40 on the two units and the common plants of TPP Kostolac B.

  3. Control and protection are redundant; the turbine protection channels are tripled.

  4. ALSTOM TGC, LMZ and the institute’s own turbine governors, electrostatic precipitators, generator and block transformer protection (KTA), AK1703 ACP systems.

  5. Monitoring, control, archiving and statistics on the VIEW packages. The advanced alarm system speeds up fault finding; the long archive lets every event be analyzed.

The unit

System components

  • VIEW T-Power

    DCS for thermal plants: unit control, integration of the turbine governor, precipitators, protections.

  • VIEW H-Power

    DCS for hydro plants: control and protection of the hydro unit and block transformer.

  • Atlas Max

    The institute’s redundant controllers for the process areas.

  • VIEW packages

    Monitoring, control, archiving, analysis and statistics; the current release is VIEW4.

  • Turbine governor

    The institute’s own governor in one system with the DCS — coordinated boiler-turbine mode.

Protocols and standards

  • IEC 61131
  • Redundant controllers
  • Tripled turbine protection channels
  • ALSTOM TGC
  • LMZ
  • KTA
  • AK1703 ACP

Where it is used

  • Thermal power plantsUnits of 125–348.5 MW: boiler, turbine, generator, common plants.
  • Hydro power plantsHydro units and block transformers, the plant’s central control.
  • ModernizationReplacing obsolete control systems during overhauls, in phases.

Institut Mihajlo Pupin

The institute’s experience

  1. 2008–2014
    TPP Kostolac B, units B1 and B2Control system modernization in phases: more than 40 redundant controllers, a new turbine governor
  2. 2019
    TPP MoravaDCS overhaul
  3. —
    TPP Nikola Tesla A1, A2, A4Integration of electrostatic precipitators; on A4 of an ALSTOM TGC governor
  4. 2006
    HPP Đerdap 2Modernization of the unit and block transformer control boards, integration of LMZ governors and generator thermal protection
  5. —
    HPP Vrla 1Integration of the existing turbine governors

Solution selection

Inquiry: DCS VIEW Power

Describe the site and the task. Trinone Group selects a solution on the institute’s systems together with the group members’ equipment and prepares the proposal and the documentation.

  • The site and the task
  • System and equipment scope
  • Proposal and documentation
Request a solution

QuestionnaireFill in onlineFill in by hand

Case study · Institut Mihajlo Pupin Distributed control systems (DCS) 2 pages · EN
Download PDF

← → turn · click to zoom · Esc close

Case study · Institut Mihajlo Pupin TPP Kostolac B · MRU modernization 2 pages · EN
Download PDF

← → turn · click to zoom · Esc close